· 9/15/1874
St. Clair v. Perrine
Citations
- 75 Ill. 366
Syllabus
<p>Consideration—forbearing legal proceeding. Where a contractor for the erection of a building, who had employed sub-contractors to furnish materials, left the work unfinished, and the sub-contractors unpaid, and they claimed a lien on the building, and the owner promised to pay them their demand if they would take no steps to enforce their lien: Held, that this was a good consideration for the owner’s promise.</p>
Judges: Breese
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.