Skip to main content
· 9/15/1874

St. Clair v. Perrine

Citations

  • 75 Ill. 366

Syllabus

<p>Consideration—forbearing legal proceeding. Where a contractor for the erection of a building, who had employed sub-contractors to furnish materials, left the work unfinished, and the sub-contractors unpaid, and they claimed a lien on the building, and the owner promised to pay them their demand if they would take no steps to enforce their lien: Held, that this was a good consideration for the owner’s promise.</p>

Judges: Breese

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.