· 3/13/1998
Southwestern Elec. Power Co. v. Burlington Northern Railroad Co.
Citations
- 966 S.W.2d 467
- 41 Tex. Sup. Ct. J. 529
- 1998 Tex. LEXIS 40
- 1998 WL 107920
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- holding that a claim for restitution based on a theory of unjust enrichment was invalid absent any overcharges on the contract
- holding that an evidentiary ruling was not harmful because in light of other testimony and similar evidence, the excluded evidence would have been cumulative
- holding that objecting party waived appellate complaint regarding admission of evidence when it invited the alleged error by being the first party to introduce the allegedly objectionable evidence
- holding that it was “unable to locate any case in which an unjust enrichment remedy was allowed when the contested issue was governed by a valid contract”
- holding that objecting party waived appellate complaint regarding admission of evidence when it invited the alleged error by being the first party to introduce the allegedly objectionable evidence
- observing that overpay-ments under a contract can be recovered under a theory of restitution or unjust enrichment
Source: CourtListener parenthetical corpus (CC0).
Judges: Owen
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.