Smoot v. United States
Citations
- 237 U.S. 38
- 35 S. Ct. 540
- 59 L. Ed. 829
- 1915 U.S. LEXIS 1308
- 50 Ct. Cl. 404
Syllabus
<p>A letter from the Government engineer in charge to a contractor, who had, under written contract with the United States, agreed to ’ furnish a specified amount of material at a specified price, that a larger amount of material would probably be required, held in this case not to be a contract for the additional amount ,or a modification of the original contract.</p> <p>As a general rule, specific or, individual marks and figures control generic ones; and there is an analogy between the control of specific figures over estimates and that of monuments over distances. Braw- '■ ley v. United States, 96 U. S. 168.</p>
Judges: Holmes, McReynolds
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.