· 2/6/1981
Sime Construction Co. v. Washington Public Power Supply System
Citations
- 621 P.2d 1299
- 28 Wash. App. 10
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- affirming dismissal of contractor's claim where contractor failed to comply with contractual notice procedures
- affirming dismissal of contractor’s claim where contractor failed to comply with contractual notice procedures
- rejecting the subcontractor’s argument that the subcontract incorporated the prime contract only to the extent it defined the scope of the subcontractors work and holding that the notice procedures for delay damages were also incorporated into the subcontract
- owner was prejudiced by contractor's lack of written notice because it could have made more favorable, alternate arrangements
- owner was prejudiced by contractor’s lack of written notice because it could have made more favorable, alternate arrangements
- subcontract provided that “Subcontract documents include all the below listed items, all of which are incorporated herein and made part hereof by reference hereto.”
Source: CourtListener parenthetical corpus (CC0).
Judges: Green
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.