Scotto v. Scotto
Citations
- 66 A.D.2d 839
- 411 N.Y.S.2d 400
- 1978 N.Y. App. Div. LEXIS 14175
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- noting that “it is well settled that the subcontractor or supplier of a general contractor on a construction project is not invested with third-party beneficiary status” and are, instead, “incidental beneficiaries”
- denying motion to dismiss third-party beneficiary claim because “the parties have not submitted the contracts”
- “Only an intended beneficiary of a contract may maintain an action as a third party; an incidental beneficiary may not.”
- necessary to demonstrate an intent that performance benefit the third party
- intent that performance benefit the third party required
Source: CourtListener parenthetical corpus (CC0).
Sourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.