S. J. Groves & Sons Company v. Warner Company

Citations

  • 576 F.2d 524
  • 24 U.C.C. Rep. Serv. (West) 1
  • 1978 U.S. App. LEXIS 11626

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • subcontractor not obliged to mitigate damages by contracting for additional supply of concrete when supplier would not perform and supplier was in as good a position as subcontractor to obtain a supplemental supply
  • Under Pennsylvania law, the burden of proving that losses from breach of contract could have been avoided by reasonable effort and expense must be borne by party who has broken contract

Source: CourtListener parenthetical corpus (CC0).

Judges: Weis, Aldisert, Van Dusen Weis