Skip to main content
· 5/8/1998

Roanoke Properties Ltd. Part. v. Roanoke Harbour, Inc.

Citations

  • 348 N.C. 284

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • as a matter of law, government did not have constructive notice of bidder’s mistake where bid was 32% below government’s estimate, when majority of bids were also lower than the government’s estimate
  • “A contractor cannot recover for a mistake in judgment”

Source: CourtListener parenthetical corpus (CC0).

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.