· 9/20/2017
Rivers v. Exec. Dir. of the Utah Dep't of Envtl. Quality & the Dir. of the Utah Div. of Water Quality
Citations
- 417 P.3d 57
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- noting that the remaining contract balance was insufficient to cover all of the assessed liquidated damages, and that the government sought in its counterclaim all of the liquidated damages assessed
- “After the contracting officer issues a final decision on a claim, the contractor may éither appeal to the. appropriate board of appeals or to the Court of Federal Claims.”
Source: CourtListener parenthetical corpus (CC0).
Judges: Himonas
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).