Regina Construction Corp. v. Envirmech Contracting Corp.
Citations
- 565 A.2d 693
- 80 Md. App. 662
- 1989 Md. App. LEXIS 191
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- the claim as to the subcontract’s validity is an issue to be decided by the arbitrator
- claim regarding the validity of a subcontract is for the arbitrator to decide
Source: CourtListener parenthetical corpus (CC0).
Judges: Moylan, Wilner, Garrity
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).