· 4/12/1983
Post Tensioned Engineering Corp. v. Fairways Plaza Associates
Citations
- 429 So. 2d 1212
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- holding that if an arbitrable issue is severable from the issue to be litigated, a stay of proceedings need only encompass the severable issue
- staying both arbitrable claim that general contractor failed to follow design specifications and non-severable, non-arbitrable respondeat superior claims against subcontractors, but allowing to proceed severable claims against design engineer that building design itself was faulty
- staying both arbitrable claim that general contractor failed to follow design specifications and non-severable, non-arbitrable respondeat superior claims against subcontractors, but allowing to proceed severable claims against design engineer that building design itself was faulty
Source: CourtListener parenthetical corpus (CC0).
Judges: Schwartz, C.J., and Daniel S. Pearson and Jorgenson
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.