Porto Rico v. Title Guaranty & Surety Co.

Citations

  • 227 U.S. 382
  • 33 S. Ct. 362
  • 57 L. Ed. 561
  • 1913 U.S. LEXIS 2310

Syllabus

<p>In this case held that a bond given in pursuance of an ordinance, for faithful performance of a contract, was solely for the complete result at the end of the period specified, and that it did not permit a recovery of the whole penalty upon any intermediate breach.</p> <p>Breaches of subordinate requirements, which are specified in a contract for a public utility and bond for performance and arc simply means to an end, cannot be made the basis of recovering the whole penalty after final completion or after cancellation by the obligee of the franchise.</p> <p>If within time for completion of a public utility authorized by ordinance, the municipality itself makes performance impossible, it cannot, under any system of law in Porto Rico or elsewhere, recover upon the bond for failure to perform.</p>

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • “If, within the time allowed for performance, the plaintiff made performance impossible, it is unimaginable that any civilized system of law would allow it to recover upon the bond for a failure to perform”

Source: CourtListener parenthetical corpus (CC0).

Judges: Holmes