Portland General Electric Co. v. Bonneville Power Administration
Citations
- 501 F.3d 1009
- 2007 U.S. App. LEXIS 10342
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- holding that BPA’s statutory authority to enter into settlement agreements pursuant to section 2(f) of the Project Act is cabined by the agency’s other statutory obligations
- holding that BPA’s statutory authority to enter into settlement agreements pursuant to section 2(f) of the Project Act is cabined by the agency’s other statutory obligations
- holding that BPA’s statutory authority to enter into settlement agreements pursuant to section 2(f) of the Project Act is cabined by the agency’s other statutory obligations
- holding that BPA’s statutory authority to enter into settlement agreements pursuant to section 2(f) of the Project Act is cabined by the agency’s other statutory obligations
- explaining that failure to exhaust is excused where “[the] agency ... had an opportunity to consider the issue[,] .... even if the issue was considered sua sponte by the agency”
- noting that BPA is “charg[ed] to function as a business.”
Source: CourtListener parenthetical corpus (CC0).
Judges: Reinhardt, Fletcher, Bybee
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).