Poirier & McLane Corp. v. United States
Citations
- 120 F. Supp. 209
- 128 Ct. Cl. 117
- 1954 U.S. Ct. Cl. LEXIS 124
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- government responsible for increased cost where both parties were unaware of the correct wage rate, and intended that the correct rate be paid
- government responsible for increased cost where both parties were unaware of the correct wage rate, and intended that the correct rate be paid
- reformation granted where mutual mistake of fact was the parties’ mutual ignorance of the actual prevailing wage rate for area laborers, resulting in costs above those stated in written contract
- reformation granted where mutual mistake of fact was the parties’ mutual ignorance of the actual prevailing wage rate for area laborers, resulting in costs above those stated in written contract
Source: CourtListener parenthetical corpus (CC0).
Judges: Jones, Littleton, Whitaker, Madden
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.