Pierce v. Cook & Co., Inc.
Citations
- 437 F.2d 1119
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- trial court properly concluded that provision for extension of time in case of delay precluded recovery of monetary damages for such delay
- “The words ‘subject to’ usually indicate a condi- tion to one party’s duty of performance and not a promise by the other.”
- extension of time clause “does not necessarily provide an exemption …. for [the general contractor’s] delay”
- “unreasonable delay is a breach of an implied obligation not to hinder or delay the other party’s performance, in the absence of a contract clause contemplating and excusing the delay”
Source: CourtListener parenthetical corpus (CC0).
Judges: Phillips
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).