· 6/5/1973
Petition of Vermont Electric Power Company, Inc.
Citations
- 306 A.2d 687
- 131 Vt. 427
- 1973 Vt. LEXIS 328
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- stating that use of post-certification proceedings is “an accepted practice of the Board and administrative tribunals generally”
- approving process whereby Board gave parties in post-certification proceeding opportunity to comment and convince Board that hearing was necessary for further review as to location of transmission lines
- approving process whereby Board gave parties in post-certification proceeding opportunity to comment and convince Board that hearing was necessary for further review as to location of transmission lines
- approving process whereby Board gave parties in post-certification proceeding opportunity to comment and convince Board that hearing was necessary for further review as to specific route of transmission lines where Board had already approved general route for proposed line
- approving process whereby Board gave parties in post-certification proceeding opportunity to comment and convince Board that hearing was necessary for further review as to specific route of transmission lines where Board had already approved general route for proposed line
- “Only when we have reviewed the entire record and have been left with the definite and firm conviction that a mistake has been committed will we hold a finding to be clearly erroneous.”
Source: CourtListener parenthetical corpus (CC0).
Judges: Shangraw, Barney, Smith, Keyser, Daley
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).