Pearson v. Puget Sound Machinery Depot

Citations

  • 99 Wash. 596
  • 169 P. 961
  • 1918 Wash. LEXIS 651

Syllabus

<p>Municipal Corporations—Improvements—Claims Against Bond —Time to Pile. The fact that some work was done after acceptance of a building as completed, does not show fraud on the part of a port commission in accepting the work by a resolution which was a matter of public record, so that the filing of a materialman’s lien against the contractor’s bond thirty-one days thereafter was too late.</p>

Judges: Mount

Read full opinion on CourtListener