Palmgreen v. Palmer's Garage, Inc.
Citations
- 383 Pa. 105
- 117 A.2d 721
- 1955 Pa. LEXIS 319
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- interest is due on ascertainable damages arising out of contract as of right from date of breach
- interest is due on ascertainable damages arising out of contract as of right from date of breach
- award of prejudgment interest is a legal right to which plaintiff is entitled
- “In all cases of contract^] interest is allowable at the legal rate from the time payment is withheld after it has become the duty of the debtor to make such payment; allowance of such interest does not depend upon discretion but is a legal right.”
- “In all cases of contract interest is allowable at the legal rate from the time payment is withheld after it has become the duty of the debtor to make such payment; allowance of such interest does not depend upon discretion but is a legal right.”
- “In all cases of contract interest is allowable at the legal rate from the time payment is withheld after it has become the duty of the debtor to make such payment; allowance of such interest does not depend upon discretion but is a legal right.”
Source: CourtListener parenthetical corpus (CC0).
Judges: Stern, Steen, Stearne, Jones, Mush, Arnold
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).