Oman-Fischbach International (Jv) v. Robert Pirie, Secretary of the Navy

Citations

  • 276 F.3d 1380
  • 32 Envtl. L. Rep. (Envtl. Law Inst.) 20437
  • 2002 U.S. App. LEXIS 768
  • 2002 WL 63363

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • noting that the contracting officer denied the contractor's REA, which was treated as a denied claim
  • “The contracting officer issued a final decision denying [the contractor’s claim for an equitable adjustment] but reaffirmed the amount awarded in [unilateral] Modification P00053.”
  • “Paragraph (a) [of FAR 52.236-3, SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984)] makes clear that the burden of [inspecting the site] is the responsibility of the contractor”
  • “Unless the parties in unmis- takable terms agreed to shift the risk of [the contract] due to acts by [a third-party] military, no liability on the part of the [U.S.] attaches from such acts.”

Source: CourtListener parenthetical corpus (CC0).

Judges: Mayer, Clevenger, Linn

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.