· 4/18/1913
Olive Hill Fire Brick Co. v. Mullins
Citations
- 153 Ky. 293
- 155 S.W. 372
- 1913 Ky. LEXIS 818
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- stating that the general rule is that a plaintiff must point to a specific provision in the contract that was breached by the defendant
- “[A]s a general rule, a plaintiff suing for breach of contract must point to a specific provision in the contract that was breached by the defendant.”
- “[T]he Complaint merely concludes that [the defendant] ‘breached its obligations’ under the two agreements at issue, without specifying which provision or terms of the two contracts the [the defendant] allegedly breached.”
- “This Court and others throughout this Circuit have consistently indicated that, as a general rule, ‘a plaintiff suing for breach of contract must point to a specific provision in the contract that was breached by the defendant’”
Source: CourtListener parenthetical corpus (CC0).
Judges: Hobson
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.