· 3/25/1921

Northwestern Debenture Co. v. Thurmond

Citations

  • 115 Wash. 130
  • 196 P. 571
  • 1921 Wash. LEXIS 676

Syllabus

<p>Set-off and Counterclaim (3)—Contract. In an action to recover for extras due upon a building contract, where the defense was that the owner of the building should be allowed an offset for failure of full performance of skylight specifications, but without making any counterclaim therefor, and the evidence showed the cost of installing the additional skylight was in excess of the amount due for extras, the defendant was entitled to a dismissal of the action.</p>

Judges: Bridges