Northwestern Debenture Co. v. Thurmond
Citations
- 115 Wash. 130
- 196 P. 571
- 1921 Wash. LEXIS 676
Syllabus
<p>Set-off and Counterclaim (3)—Contract. In an action to recover for extras due upon a building contract, where the defense was that the owner of the building should be allowed an offset for failure of full performance of skylight specifications, but without making any counterclaim therefor, and the evidence showed the cost of installing the additional skylight was in excess of the amount due for extras, the defendant was entitled to a dismissal of the action.</p>
Judges: Bridges
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.