· 2/20/2014
New Jersey Board of Public Utilities v. Federal Energy Regulatory Commission
Citations
- 744 F.3d 74
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- explaining that state-mandated resources consisted of “any planned resource being developed in response to a state regulatory or legislative mandate to resolve a projected capacity shortfall”
- explaining that state-mandated resources consisted of “any planned resource being developed in response to a state regulatory or legislative mandate to resolve a projected capacity shortfall”
- explaining that the capacity market ensures that “there are enough . . . generators connected to the transmission grid for the system to function at peak load.”
- explaining that the capacity market ensures that “there are enough . . . generators connected to the transmission grid for the system to function at peak load.”
- explaining that the capacity market ensures that “there are enough . . . generators connected to the transmission grid for the system to function at peak load.”
- reviewing whether FERC’s elimination of a state-mandated exception was “in excess of statutory jurisdiction, authority, or limitations, or short of statutory right” (internal quotation marks omitted
Source: CourtListener parenthetical corpus (CC0).
Judges: Rendell, Jordan, Greenaway
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.