New Jersey Board of Public Utilities v. Federal Energy Regulatory Commission

Citations

  • 744 F.3d 74

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • explaining that state-mandated resources consisted of “any planned resource being developed in response to a state regulatory or legislative mandate to resolve a projected capacity shortfall”
  • explaining that state-mandated resources consisted of “any planned resource being developed in response to a state regulatory or legislative mandate to resolve a projected capacity shortfall”
  • explaining that the capacity market ensures that “there are enough . . . generators connected to the transmission grid for the system to function at peak load.”
  • explaining that the capacity market ensures that “there are enough . . . generators connected to the transmission grid for the system to function at peak load.”
  • explaining that the capacity market ensures that “there are enough . . . generators connected to the transmission grid for the system to function at peak load.”
  • reviewing whether FERC’s elimination of a state-mandated exception was “in excess of statutory jurisdiction, authority, or limitations, or short of statutory right” (internal quotation marks omitted

Source: CourtListener parenthetical corpus (CC0).

Judges: Rendell, Jordan, Greenaway

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.