Nether Providence Township School District v. Mercur
Citations
- 46 Pa. Super. 470
- 1911 Pa. Super. LEXIS 299
Syllabus
<p>Equity — Injunction—Damages—Contract—School building — Directors.</p> <p>Where a board of school directors have accepted a bid for the erection of a school building, and the contract with plans and specifications has been prepared and signed by the contractor, but before the officers of the board have signed it, an injunction issued restraining further action, and subsequently on the injunction being dissolved, the contract is signed and the building erected, the complainant at whose instance the injunction issued, will be liable on his injunction bond for the loss sustained by the contractor from the delay resulting from the injunction.</p>
Judges: Beaver, Head, Henderson, Morrison, Orlady, Porter, Rice
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.