· 7/14/2005
MW Erectors, Inc. v. Niederhauser Ornamental & Metal Works Co.
Citations
- 115 P.3d 41
- 30 Cal. Rptr. 3d 755
- 36 Cal. 4th 412
- 2005 Daily Journal DAR 8415
- 2005 Cal. Daily Op. Serv. 6163
- 2005 Cal. LEXIS 7443
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- holding that “application of the void contract principle is inappropriate” where a contractor, “though unlicensed when a contract for services was entered, was fully licensed at all times during performance”
- “The words ‘at all times’ convey the Legislature’s obvious 14 intent to impose a stiff all-or-nothing penalty for unlicensed work . . . .”
- a contractor is unlicensed if its “licensure 2 lapsed at any time during the work”
Source: CourtListener parenthetical corpus (CC0).
Judges: Baxter
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.