Muckle v. Payne
Citations
- 198 Pa. 444
- 48 A. 413
- 1901 Pa. LEXIS 816
Syllabus
<p>Contract—Building contract—Specifications—Elevators—Air cushions— Tests.</p> <p>Where a building contract provides a certain make of elevators and that certain patented air cushions shall be provided, and that the air cushions shall be subjected to certain tests, the contractor may recover for the elevators and air cushions without the test having been made, where it appears that he constructed the air cushions of the depth appearing upon the architect’s plan submitted to him, although the specifications were silent as to the depth of the cushions.</p>
Judges: Brown, Fell, McCollum, Mestrbzat, Potter