· 3/12/1982
Muchmore Equipment, Inc. v. Grover
Citations
- 315 N.W.2d 92
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- holding that even though the contract included a finance charge, “this contract itself was not on ‘credit’; it called for the balance in full upon completion of the building”
- holding that a contract for the construction of a grain bin did not extend any right to defer payment because the contract required payment in full upon completion of the work
Source: CourtListener parenthetical corpus (CC0).
Judges: Reynoldson, Uhlenhopp, Harris, McGiverin, Schultz
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.