Skip to main content
· 12/31/1969

Miller Bros. Industrial Sheet Metal Corp. v. La Salle National Bank

Citations

  • 255 N.E.2d 755
  • 119 Ill. App. 2d 23
  • 1969 Ill. App. LEXIS 1706

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • time in which to file mechanic’s lien not extended by “maintenance or correction of completed work” as opposed to work that completes the contract itself
  • time in which to file mechanic's lien not extended by \maintenance or correction of completed work\ as opposed to work that completes the contract itself
  • work that is in the nature of maintenance or correction of a completed job rather than work needed for “the completion of the contract itself’ will not extend the time in which to file a lien claim
  • work that is in the nature of maintenance or correction of a completed job rather than work needed for \the completion of the contract itself\ will not extend the time in which to file a lien claim

Source: CourtListener parenthetical corpus (CC0).

Judges: Abrahamson

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.