Miller Bros. Industrial Sheet Metal Corp. v. La Salle National Bank
Citations
- 255 N.E.2d 755
- 119 Ill. App. 2d 23
- 1969 Ill. App. LEXIS 1706
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- time in which to file mechanic’s lien not extended by “maintenance or correction of completed work” as opposed to work that completes the contract itself
- time in which to file mechanic's lien not extended by \maintenance or correction of completed work\ as opposed to work that completes the contract itself
- work that is in the nature of maintenance or correction of a completed job rather than work needed for “the completion of the contract itself’ will not extend the time in which to file a lien claim
- work that is in the nature of maintenance or correction of a completed job rather than work needed for \the completion of the contract itself\ will not extend the time in which to file a lien claim
Source: CourtListener parenthetical corpus (CC0).
Judges: Abrahamson
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).