Skip to main content
· 5/31/2012

Michael's Construction, Inc. v. American National Bank

Citations

  • 2012 WY 76
  • 278 P.3d 701
  • 2012 WL 1948854

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • finding that for priority purposes liens under the Wyoming Lien Act relate back to the time when “visible, on-site commencement of construction work” first occurs

Source: CourtListener parenthetical corpus (CC0).

Judges: Kite, Golden, Hill, Voigt, Burke

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.