Skip to main content
· 10/24/1956

McGraw v. Johnson

Citations

  • 126 A.2d 203
  • 42 N.J. Super. 267

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • noting that performance under contract must be completed within reasonable time where claim was based on contractor's alleged failure to complete building of home within a reasonable time

Source: CourtListener parenthetical corpus (CC0).

Judges: Judges Goldmann, Freund and Conford

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).