Skip to main content
· 7/1/1999

McDonnell Douglas Corporation, Plaintiff-Cross and General Dynamics Corporation, Plaintiff-Cross v. United States

Citations

  • 182 F.3d 1319
  • 1999 U.S. App. LEXIS 14805
  • 1999 WL 450934

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • “[A] termination for default that is unrelated to contract performance is arbitrary and capricious, and thus an abuse of the contracting officer’s discretion.”
  • “In litigation over a contractor’s failure to make progress — unlike a dispute over failure to meet a specific contract requirement or schedule — courts must always determine ex post the threshold of performance that a contractor must meet to avoid endangering performance.”

Source: CourtListener parenthetical corpus (CC0).

Judges: Mayer, Michel, Clevenger

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.