McDonnell Douglas Corporation, Plaintiff-Cross and General Dynamics Corporation, Plaintiff-Cross v. United States
Citations
- 182 F.3d 1319
- 1999 U.S. App. LEXIS 14805
- 1999 WL 450934
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- “[A] termination for default that is unrelated to contract performance is arbitrary and capricious, and thus an abuse of the contracting officer’s discretion.”
- “In litigation over a contractor’s failure to make progress — unlike a dispute over failure to meet a specific contract requirement or schedule — courts must always determine ex post the threshold of performance that a contractor must meet to avoid endangering performance.”
Source: CourtListener parenthetical corpus (CC0).
Judges: Mayer, Michel, Clevenger
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).