Maryland Steel Co. of Baltimore Cty. v. United States
Citations
- 235 U.S. 451
- 35 S. Ct. 190
- 59 L. Ed. 312
- 1915 U.S. LEXIS 1834
- 50 Ct. Cl. 401
Syllabus
<p>Although parties to a contract may agree that time is of the essence and may stipulate for liquidated damages, they may subsequently so modify the requirements as to completion that performance within the stipulated time becomes unimportant. Flynn v. Des Moines Railway, 63 Iowa, 490, approved.</p> <p>As the record in this case does not show that there was any culpable delinquency in completion of a contract for the building of a vessel, or any detriment to the Government, but that the vessel was' delivered, tested, approved and paid for without protest on the part of the Government on account of delay, and, as it does appear, the Quartermaster General had, in his discretion, orally waived the time limit in the contract, held,-that:</p> <p>In a case of contract authorized by law necessarily entered into and conducted by officers of the Government, they must necessarily have'the power to make it effective in its progress as well as in its beginning; and the oral agreement of the Quartermaster General was within the scope of his official authority and amounted to a modification of the contract. Salomon v. United States, 19 Wall. 17, followed. United States v. Bethlehem Steel Co., 205 U. S. 105, distinguished.</p>
Judges: McKenna, McReynolds
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.