Marr v. Lewis
Citations
- 31 Ark. 203
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- “In addition, to warrant a time extension, the contractor must show that the excusable event delayed activities along the critical path, which consists of activities that must be performed on schedule so as not to delay the entire project.” (citations omitted)
Source: CourtListener parenthetical corpus (CC0).