M. A. Lombard & Son Co. v. Public Building Commission

Citations

  • 428 N.E.2d 889
  • 101 Ill. App. 3d 514
  • 57 Ill. Dec. 209
  • 1981 Ill. App. LEXIS 3916

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • indicated that proof of misrepresentation or fraud would negate a waiver of damages for delay provision
  • “if the contract expressly provides for delay or if the right of recovery is expressly limited or precluded, then these provisions will control”
  • indicated that proof of misrepresentation or fraud would negate a waiver of damages for delay provision
  • no-damage-for-delay clause precludes recovery of delay damages absent proof of misrepresentation or fraud by contractee; it is presumed that parties deliberately inserted clauses with specific objectives in mind

Source: CourtListener parenthetical corpus (CC0).

Judges: Wilson