· 10/26/1942

Levine v. Levine

Citations

  • 317 U.S. 673
  • 63 S. Ct. 78

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • construction contract provision stating that engineer’s determination of disputes as to suitability of work will be “final and conclusive” is an enforceable agreement to arbitrate
  • construction contract provision stating that engineer’s determination of disputes as to suitability of work will be “final and conclusive” is an enforceable agreement to arbitrate

Source: CourtListener parenthetical corpus (CC0).

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).