· 5/21/1956
Lefkowitz v. Hummel Furniture Co.
Citations
- 385 Pa. 244
- 122 A.2d 802
- 1956 Pa. LEXIS 459
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- “[W]here no time for performance is provided in the written instrument the law implies that it shall be done within a reasonable time_”
- “[W]here no time for performance is provided in the written instrument the law implies that it shall be done within a reasonable time...”
- “[W]here no time for performance is provided in the written instrument the law implies that it shall be done within a reasonable time.... ”
- Where no time for the preparation and submission of plans was provided in a construction contract, the law implied that it shall be done within a reasonable time.
- Where no time for the preparation and submission of plans was provided in a construction contract, the law implied that it shall be done within a reasonable time.
- imposing a reasonable time when contract is silent
Source: CourtListener parenthetical corpus (CC0).
Judges: Stern, Jones, Bell, Musmanno, Arnold
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).