Lefkowitz v. Hummel Furniture Co.

Citations

  • 385 Pa. 244
  • 122 A.2d 802
  • 1956 Pa. LEXIS 459

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • “[W]here no time for performance is provided in the written instrument the law implies that it shall be done within a reasonable time_”
  • “[W]here no time for performance is provided in the written instrument the law implies that it shall be done within a reasonable time...”
  • “[W]here no time for performance is provided in the written instrument the law implies that it shall be done within a reasonable time.... ”
  • Where no time for the preparation and submission of plans was provided in a construction contract, the law implied that it shall be done within a reasonable time.
  • Where no time for the preparation and submission of plans was provided in a construction contract, the law implied that it shall be done within a reasonable time.
  • imposing a reasonable time when contract is silent

Source: CourtListener parenthetical corpus (CC0).

Judges: Stern, Jones, Bell, Musmanno, Arnold

Read full opinion on CourtListener