· 7/7/1970
Kobayashi v. Meehleis Steel Co.
Citations
- 472 P.2d 724
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- company that contracted with subcontractor to fabricate precast concrete structural columns away from the construction site held to be a “subcontractor” for mechanics’ lien purposes, and not a “materialman”
- company that contracted with subcontractor to fabricate precast concrete structural columns away from the construction site held to be a \subcontractor\ for mechanics' lien purposes, and not a \materialman\
- sub-subcontractor constructing building components away from job site considered subcontractor under mechanic’s lien law
- fact that building components constructed off-site does not defeat lien for labor and materials
- involving off-site construction of precast, pre-stressed concrete columns
Source: CourtListener parenthetical corpus (CC0).
Judges: Dufford
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.