Kobayashi v. Meehleis Steel Co.

Citations

  • 472 P.2d 724

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • company that contracted with subcontractor to fabricate precast concrete structural columns away from the construction site held to be a “subcontractor” for mechanics’ lien purposes, and not a “materialman”
  • company that contracted with subcontractor to fabricate precast concrete structural columns away from the construction site held to be a \subcontractor\ for mechanics' lien purposes, and not a \materialman\
  • sub-subcontractor constructing building components away from job site considered subcontractor under mechanic’s lien law
  • fact that building components constructed off-site does not defeat lien for labor and materials
  • involving off-site construction of precast, pre-stressed concrete columns

Source: CourtListener parenthetical corpus (CC0).

Judges: Dufford

Read full opinion on CourtListener