Kinetic Builder's, Inc.,appellant v. F. Whitten Peters, Secretary of the Air Force,appellee
Citations
- 226 F.3d 1307
- 2000 U.S. App. LEXIS 23728
- 2000 WL 1370335
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- recognizing and reviewing the ASBCA’s denial of a contractor’s claim for extended overhead costs incurred as a result of a delay in contract completion
- declining to award field overhead costs when contractor failed to show that government's actions affected the critical path
- \A project should be considered substantially completed when it is capable of being used for its intended purpose.\
Source: CourtListener parenthetical corpus (CC0).
Judges: Rader, Schall, Linn
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).