Skip to main content
· 3/30/1978

K. L. House Construction Co. v. City of Albuquerque

Citations

  • 576 P.2d 752
  • 91 N.M. 492

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • holding that disputes arising after the completion of contractual obligation were reasonably related to the contract and subject to arbitration
  • holding that if there is a reasonable relationship between the subject matter of the dispute and the general subject matter of the underlying contract, a particular disputes should be arbitrated
  • holding that, because a valid arbitration clause existed, the parties had to arbitrate all disputes when the \subject matter of the dispute has a reasonable relationship to the subject matter of the contract\
  • holding that, because a valid arbitration clause existed, the parties had to arbitrate all disputes when the \subject matter of the dispute has a reasonable relationship to the subject matter of the contract\
  • holding that because a valid arbitration clause existed, the parties had to arbitrate all disputes when the “subject matter of the dispute has a reasonable relationship to the subject matter of the contract”
  • holding that, because a valid arbitration clause existed, the parties had to arbitrate all disputes when the \subject matter of the dispute has a reasonable relationship to the subject matter of the contract\

Source: CourtListener parenthetical corpus (CC0).

Judges: Payne, McManus, Easley

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.