· 3/30/1978
K. L. House Construction Co. v. City of Albuquerque
Citations
- 576 P.2d 752
- 91 N.M. 492
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- holding that disputes arising after the completion of contractual obligation were reasonably related to the contract and subject to arbitration
- holding that if there is a reasonable relationship between the subject matter of the dispute and the general subject matter of the underlying contract, a particular disputes should be arbitrated
- holding that, because a valid arbitration clause existed, the parties had to arbitrate all disputes when the \subject matter of the dispute has a reasonable relationship to the subject matter of the contract\
- holding that, because a valid arbitration clause existed, the parties had to arbitrate all disputes when the \subject matter of the dispute has a reasonable relationship to the subject matter of the contract\
- holding that because a valid arbitration clause existed, the parties had to arbitrate all disputes when the “subject matter of the dispute has a reasonable relationship to the subject matter of the contract”
- holding that, because a valid arbitration clause existed, the parties had to arbitrate all disputes when the \subject matter of the dispute has a reasonable relationship to the subject matter of the contract\
Source: CourtListener parenthetical corpus (CC0).
Judges: Payne, McManus, Easley
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.