· 8/14/2008
Inimitable Group, L.P. v. Westwood Group Development II, Ltd.
Citations
- 264 S.W.3d 892
- 2008 Tex. App. LEXIS 6252
- 2008 WL 3540268
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- “One of the essential requisites of estoppel is a reasonable or justified reliance on the conduct or statements of the person sought to be estopped by the person seeking the benefit of the doctrine.”
- “One of the essential requisites of estoppel is a reasonable or justified reliance on the conduct or statements of the person sought to be estopped by the person seeking the benefit of the doctrine.”
- finding lack of duration term did not render contract unenforceable
- finding lack of duration term did not render contract unenforceable
Source: CourtListener parenthetical corpus (CC0).
Judges: Cayce, Livingston, Holman
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.