Independent Enterprises Inc. Thomas Lozecki v. Pittsburgh Water and Sewer Authority City of Pittsburgh

Citations

  • 103 F.3d 1165
  • 1997 U.S. App. LEXIS 313
  • 1997 WL 6335

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • stating that Federal Rule of Civil Procedure 8(e)(2) “permits inconsistency in both legal and factual allegations”
  • explaining that a low bidder’s entitlement to a state contract is “not the sort of ‘fundamental’ interest entitled to the protection of substantive due process”
  • noting that the Rule “has been interpreted to mean that a court ‘may not construe [a plaintiffs] first claim as an admission against another alternative or inconsistent claim.’ ”
  • stating that “a substantive due process claim grounded in an arbitrary exercise of governmental authority may be maintained only where the plaintiff has been deprived of a ‘particular quality of property interest’” (quotation omitted)
  • noting that some cases involving “zoning decisions, building permits, or other governmental permission required for some intended use of land owned by the plaintiffs . . . implicat[ed] the ‘fundamental’ property interest in the ownership of land”
  • distinguishing between a disappointed bidder's Article III standing and a low bidder's right to relief under Pennsylvania's competitive bidding statutes

Source: CourtListener parenthetical corpus (CC0).

Judges: Becker, Michel, Stapleton

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.