· 5/29/1990
Howard County v. Potomac Electric Power Co.
Citations
- 573 A.2d 821
- 319 Md. 511
- 1990 Md. LEXIS 82
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- local requirement that utilities obtain special exception status under local ordinances for siting of certain transmission lines
- statutory provision vesting the Public Service Commission with “final authority” over construction permits for power transmission lines preempted zoning ordi nances regulating the location and construction of such transmission lines
- “[W]e adhere to the rule that ‘[t]he primary indicia of a legislative purpose to preempt an entire field of law is the comprehensiveness with which the General Assembly has legislated in the field,’ ” quoting Board v. Harker, 316 Md. 683, 696-697, 561 A.2d 219, 226 (1989)
Source: CourtListener parenthetical corpus (CC0).
Judges: Murphy, Eldridge, Cole, Rodowsky, McAuliffe, Adkins, Chasanow
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.