Hou-Ching Chou v. Wong
Citations
- 34 A.D.3d 642
- 824 N.Y.S.2d 436
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- \[W]hether the [owner] or other third parties may have contributed to some of the delay\ does not relieve the contractor from liability.
- “[W]hether the [owner] or other third parties may have contributed to some of the delay” does not relieve the contractor from liability.
- parties to construction contract impliedly agree not to hinder or obstruct other party’s performance
- “The delay and improper performance of the preparatory work by [defendant] ..., and not within the contemplation of the parties when their contract was executed, constituted a material breach of [defendant’s] implied obligation not to hinder or obstruct plaintiffs performance.”