Homes & Son Construction Co., Inc. v. Bolo Corp.

Citations

  • 526 P.2d 1258
  • 22 Ariz. App. 303
  • 1974 Ariz. App. LEXIS 471

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • holding that a claim is liquidated if it provides sufficient information “to enable [a defendant] to ascertain the amount owed”
  • explaining that “[m]ere differences of opinion as to the amount” of a judgment will not preclude awarding prejudgment interest
  • claim on cost plus construction contract held to be liquidated even though there was considerable dispute as to the amount of cost
  • claim on cost plus construction contract held to be liquidated even though there was considerable dispute as to the amount of cost
  • prejudgment interest available for claims wherein the evidence furnishes data which, if believed, makes it possible to compute claim with exactness
  • mere difference of opinion as to amount due does not preclude award of prejudgment interest

Source: CourtListener parenthetical corpus (CC0).

Judges: Jacobson, Haire, Eubank

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.