· 10/8/1974
Homes & Son Construction Co., Inc. v. Bolo Corp.
Citations
- 526 P.2d 1258
- 22 Ariz. App. 303
- 1974 Ariz. App. LEXIS 471
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- holding that a claim is liquidated if it provides sufficient information “to enable [a defendant] to ascertain the amount owed”
- explaining that “[m]ere differences of opinion as to the amount” of a judgment will not preclude awarding prejudgment interest
- claim on cost plus construction contract held to be liquidated even though there was considerable dispute as to the amount of cost
- claim on cost plus construction contract held to be liquidated even though there was considerable dispute as to the amount of cost
- prejudgment interest available for claims wherein the evidence furnishes data which, if believed, makes it possible to compute claim with exactness
- mere difference of opinion as to amount due does not preclude award of prejudgment interest
Source: CourtListener parenthetical corpus (CC0).
Judges: Jacobson, Haire, Eubank
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).