Guatay Christian Fellowship v. County of San Diego

Citations

  • 670 F.3d 957
  • 2011 U.S. App. LEXIS 25581
  • 2011 WL 6450742

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • ruling that the plaintiff could not reasonably rely on, among other things, electrical permits issued by the county to a third party to establish reasonable reliance for equitable estoppel because the plaintiff only learned of that permit through discovery
  • explaining that RLUIPA claims are ripe when there is finality, but not exhaustion of administrative remedies
  • explaining that state law creates the “underlying substantive interest of a due process claim”
  • explaining that without knowing the “definitive, particularized obligations” that resulted from a land use application and review, “we cannot determine whether this permit application process itself constitutes a substantial burden on the Church”
  • applying “the Williamson County final decision requirement [] and approv[ing] the dismissal of the Church’s RLUIPA claims as unripe for lack of a final decision”
  • dismissing aspects of RLUIPA claims related to a church’s ability to operate without a use permit for religious assembly, since some issues had not yet been addressed by the city

Source: CourtListener parenthetical corpus (CC0).

Judges: Hawkins, Fisher, Wolf

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.