· 2/1/1983
Grenier v. Compratt Construction Co.
Citations
- 189 Conn. 144
- 454 A.2d 1289
- 1983 Conn. LEXIS 434
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- \The fact that a contract states a date for performance does not necessarily make time of the essence.\
- “The fact that a contract states a date for performance does not necessarily make time of the essence.”
- “The fact that a contract states a date for performance does not necessarily make time of the essence.”
- “contracting parties are free to impose conditions upon contractual liability”
- contract to purchase real estate contingent on environmental agencies' approvals
- ten day delay not unreasonable
Source: CourtListener parenthetical corpus (CC0).
Judges: Speziale, Peters, Parskey, Shea, Grillo
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.