· 8/30/1912
Grant v. Lilienthal
Citations
- 70 Wash. 57
- 125 P. 1009
- 1912 Wash. LEXIS 999
Syllabus
<p>Contracts — Pebfobmance—Evidence—Sufficiency. Findings that a subcontractor completed his grading contract are sustained by evidence that the assistant city engineer set stakes to indicate the final line of the grade, that the contractor graded to the line marked, and that the work was finished with such grading.</p>
Judges: Morris
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.