Gordon R. England, Secretary of the Navy v. The Sherman R. Smoot Corp.
Citations
- 388 F.3d 844
- 2004 U.S. App. LEXIS 22968
- 2004 WL 2453887
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- concluding that “mere grant by the government of a contract extension does not indicate that the government is at fault”
- concluding that a rebuttable presumption that the government is at fault for delay when the government ex- tended the period of contract performance is at odds with the Contract Disputes Act
- finding that payment of a claim after issuance of the modifications purporting to constitute an accord manifested that the parties did not construe the modifications as a release
- “A delay in a construction contract is excusable if it arises from either the government’s action or external forces.”
- \McMullan presumption is contrary to the CDA\
Source: CourtListener parenthetical corpus (CC0).
Judges: Lourie, Schall, Dyk
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.