· 2/17/1987
Glass v. STEWART TITLE GUARANTY COMPANY
Citations
- 354 S.E.2d 187
- 181 Ga. App. 804
- 1987 Ga. App. LEXIS 1566
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- “In the case of a condition precedent, the condition must be performed before the contract becomes absolute and obligatory upon the other party.”
- “In the case of a condition precedent, the condition must be performed before the contract becomes absolute and obligatory upon the other party.”
Source: CourtListener parenthetical corpus (CC0).
Judges: Carley, McMurray, Pope
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).