Gevyn Construction Corp. v. The United States
Citations
- 827 F.2d 752
- 34 Cont. Cas. Fed. 75,350
- 1987 U.S. App. LEXIS 497
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- explaining that interest on bank borrowings for changed work would be permissible either if it was directly traced to a specific loan or a necessity for increased borrowing is shown to have been required by extra work or delay caused by the government
- “[28 U.S.C. §] 2516(a) does not bar an interest award as part of an equitable adjustment under a fixed-price contract if the contractor has actually paid interest because of the government’s delay in payment”
- “[28 U.S.C. §] 2516(a) does not bar an interest award as part of an equitable adjustment under a fixed- price contract if the contractor has actually paid interest because of the government’s delay in payment.”
Source: CourtListener parenthetical corpus (CC0).
Judges: Markey, Bennett, Smith
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.