· 12/13/1984
Frank L. Pirtz Construction, Inc. v. Hardin Town Pump, Inc.
Citations
- 692 P.2d 460
- 214 Mont. 131
- 1984 Mont. LEXIS 1125
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- plaintiff construction company entitled to prejudgment interest from the “day it was entitled to payment,” which was the day construction project substantially complete
- lien filed more than six months after last working day but less than ninety days after construction company’s subcontractor was called in by owner to re-install carpet was timely, even though the carpeting work, valued at approximately $500, was not billed to the owner
Source: CourtListener parenthetical corpus (CC0).
Judges: Sheehy, Haswell, Weber, Gulbrandson, Shea
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).