Flynn v. Dougherty
Citations
- 3 Cal. Unrep. 412
- 26 P. 831
- 1891 Cal. LEXIS 1289
Syllabus
<p>Building Contract—Bond.—Where in an Action for a Breach of contract it appeared that defendant verbally accepted plaintiff’s written offer to furnish stone for a building defendant had undertaken to build, and that plaintiff was required, as one of the conditions, to execute a bond for the performance of the work and to commence the work as soon as possible, the failure of plaintiff to furnish or tender the bond within eight or nine days precludes his right to recover prospective profits, when nothing has been done under the bid.</p>
Judges: Vanclief
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).