Skip to main content
· 5/30/1891

Flynn v. Dougherty

Citations

  • 3 Cal. Unrep. 412
  • 26 P. 831
  • 1891 Cal. LEXIS 1289

Syllabus

<p>Building Contract—Bond.—Where in an Action for a Breach of contract it appeared that defendant verbally accepted plaintiff’s written offer to furnish stone for a building defendant had undertaken to build, and that plaintiff was required, as one of the conditions, to execute a bond for the performance of the work and to commence the work as soon as possible, the failure of plaintiff to furnish or tender the bond within eight or nine days precludes his right to recover prospective profits, when nothing has been done under the bid.</p>

Judges: Vanclief

Read full opinion on CourtListener

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.